Home Practice Areas About Us Team Bios News Case Studies Contact Us
Aldrich Eike, P.C.
Case Studies
On This Page...

Representative Defect Cases – Commercial/Institutional

American Honda Parts Distribution and Training Center

American Honda’s parts distribution and training facility in Gresham, Oregon experienced a roof collapse during a Christmas snowstorm. Thereafter, extensive design and construction defects were discovered throughout the facility. Aldrich Eike was retained to pursue claims against the project architect/engineer, the general contractor, the structural steel subcontractor and the special inspector on the project. The case presented significant legal and technical factual hurdles, including statute of limitation issues, causation issues, contract vs. tort issues, construction vs. design issues, property damage vs. defect issues (including present vs. future damage), comparative fault and contributory negligence issues, tilt-up construction and engineering issues, snow load analysis issues, repair costs, accounting issues and allocation and apportionment issues. Following a five-week trial and three days of deliberation, the jury returned a verdict in favor of American Honda for $11.8 million in total damages – the largest construction defect jury verdict in Oregon.

Wild Horse Resort and Casino

Aldrich Eike represented the Confederated Tribes of the Umatilla Indian Reservation regarding defects in a large casino expansion that resulted (in large part) from the general contractor going bankrupt and abandoning the project before substantial completion. Defects involved the flooring system, the roof system, and the HVAC system. A settlement with the general contractor’s liability insurer and bond company was achieved, as well as settlements with certain subcontractors. A three week arbitration was necessary to resolve the HVAC claims, in which the Tribe prevailed and was awarded damages and attorneys fees. All total, the Tribe achieved a 2.4 million dollar recovery for the defects and damages on a very difficult claim.

Devonwood Equestrian Center

Aldrich Eike represented the owner of a large equestrian arena building that suffered from roof and framing defects. On the second day of trial, a high six figure settlement was reached that reimbursed repair costs and damages despite the numerous legal and factual difficulties the case presented.

Irvington Corner Retail Center

Aldrich Eike represented the owner/developer of a boutique retail center that suffered from stucco defects in its high end artisan finish. The first day of trial, a settlement was reached that reimbursed repair costs. A special challenge in this matter was addressing tenant impacts during repairs.

Four Points Hotel

Aldrich Eike represented the general contractor in litigation against subcontractors for reimbursement of repair costs the general contractor incurred in repairing subcontractors’ defective work for owner. The general contractor obtained a substantial six-figure settlement which reimbursed all costs and attorney fees, while maintaining a positive relationship with the owner.

Community Action Organization

Community Action is a private non-profit corporation organized to provide services to low income families and children in Washington County. Aldrich Eike agreed to represent Community Action at a discounted rate in its suit against the original builder of its administrative building and Head Start childcare center. We successfully negotiated a settlement over half a million dollars despite significant legal and factual hurdles.

Gerber Properties

Aldrich Eike represented the owner of two office buildings regarding construction defects.  The original contractor repaired the defects, and repair costs were reimbursed by insurance carriers.  

University Station

Aldrich Eike represented the owner/developer of University Station in Salem, Oregon.  Again, the Aldrich Eike firm adopted a two-pronged approach to seek reimbursement of repair costs (property insurance claim; litigation against the builder) netting a seven figure recovery.  

Pacific Place Retail/Office Center

Aldrich Eike represented the owner/developer of the Pacific Place Retail/Office Center in two separate litigations to recover repair costs. The first litigation was filed against the builder (and its subcontractors and suppliers) for defects and water intrusion damages. The second litigation was filed against the owner/developer’s property insurance company for coverage for the severely damaged and rotten structural members (i.e., “collapse” conditions). In the property insurance litigation, the federal court issued an opinion on insurance coverage that is beneficial to property owners throughout Oregon. See Richardson v. Travelers Insurance Company, 2004 WL 1173186 (D. Or. May 25, 2004). See also Schray v. Fireman’s Fund, 402 F Supp 1212 (D. Or 20050). Both cases were successfully resolved, and allowed the owner/developer full recovery of repair costs and attorneys fees.

Thomas Edison

Aldrich Eike represented Thomas Edison School with regard to construction defect claims.  Aldrich Eike negotiated a repair agreement with the original contractor and architect. Repair costs were reimbursed by the insurance carriers, leading to a successful resolution after minimal litigation.  

Wilsonville Business Center/148th Airport Way Industrial Park

Aldrich Eike represented the developer/owner of two office complexes regarding construction defects.  Aldrich Eike worked out an agreement wherefore the original contractors and subcontractors would come back and conduct repairs, and the developer/owner would be reimbursed full repair costs from the insurance carriers.  The case involved minimal litigation.

Back to top

Representative Defect Cases – Apartment Buildings

The Commons

Aldrich Eike represented the owners of a 3-building, 284-unit, mixed-use residential community that provided low-income housing, senior housing, and traditional market-rate apartments. The case represented many technical and legal challenges and required a full team effort to resolve. Our office obtained a settlement of $5.7 million dollars, which will likely provide funding for nearly all of the necessary repairs.

Willamette Estates

Aldrich Eike represented the owner/developer/builder of a large luxury Apartment complex named Willamette Estates in Salem, Oregon in pursuing claims against the civil engineer and architect of record for the construction of the project. The claims were for expenses and repair costs incurred in defending claims levied against the client for alleged violations of the United States Department of Housing and Urban Development Fair Housing Act. The civil engineer and architect were defended by seasoned attorneys from the two largest law firms in Oregon, Stoel Rives and Schwabe Williamson and Wyatt. After over two years of fierce technical code driven litigation, Aldrich Eike obtained a large six figure settlement from a combination of the civil engineer and architect and their insurance carriers.

Terrazzo Properties

Aldrich Eike represented the owner of a 51 unit apartment complex that suffered from a variety of construction defects, including foundation, siding and roof defects. Utilizing efficient litigation strategies, the Aldrich Eike firm successfully negotiated a seven figure settlement that reimbursed ongoing repair costs, well in advance of trial.

Nuevo Amanacer

Nuevo Amanacer is a non-profit low-income housing complex for persons performing agri-farm related work in Marion County. Aldrich Eike represented the owners in their first-party insurance claim, and successfully obtained nearly $300,000 for collapse-related damages to both phases of the complex. In addition, Aldrich Eike litigated against the contractors of the Phase II development and resolved those claims for a settlement of an additional $475,000.

Cascade Crossing

Aldrich Eike represented the owner of a six-building, 74 unit apartment complex in Portland suing the original builder for defects related primarily to deck construction.  We obtained a settlement from the builder sufficient to completely rebuild all decks at the property. 

Emerald Village

Aldrich Eike represented the owner of a 96-unit apartment complex in Springfield, Oregon suing the original builder for defects related to vinyl siding installation. Near the end of litigation, the builder agreed to completely remove and re-install the siding, and the builder paid an additional amount to cover the owner’s attorney fees.  

Aginsky

Aldrich Eike represented the owners of an apartment complex that suffered damage as a result of a re-roofing process gone awry.  Recovery was made against the roofing contractor for damages after litigation despite a lien claim by the roofer.  

Fanno Creek Apartments

Aldrich Eike represented the owner/developer/general contractor regarding reimbursement for repair costs spent to correct failing decks at a large apartment complex.  Aldrich Eike adopted a two-pronged approach to seek reimbursement:  first, we obtained settlement with the property insurance company regarding collapse conditions on the decks; secondly, we filed legal action against responsible subcontractors leading to settlement. 

Back to top

Representative Defect Cases – Condominium/Townhomes

Streetcar Lofts Condominiums

Aldrich Eike represented the condominium association in pursuing design and construction defect claims against the architect, developer and general contractor of this signature condominium project in Portland’s Pearl District.  Following the building’s construction in 2001, many of the condominium owners experienced water intrusion into their units from a myriad of design and construction defects, but the developer contractor, and architect claimed they had fixed all problems and that caulking maintenance by the HOA was the answer.  On the eve of trial, the Aldrich Eike Team obtained a $2.1+ million settlement (more than four times what the defense had contended was necessary for repairs), which allowed the building to finally be properly repaired, resolving once and for all the water intrusion issues with the condominiums.

Orenco Station Live/Work Townhomes

Aldrich Eike represented the Association of Unit Owners and individual unit owners at Orenco Station Live/Work Townhomes, a unique 6-building, 28-unit multi-use townhome development, consisting of commercial, retail, and residential units.  This case is the pinnacle of a new litigation strategy developed by Aldrich Eike whereby, during the course of litigation, repairs are completed on a single test building to establish necessary repair scope and costs.  The defect, damage, and repair cost information gained from the test building is then applied to the remaining buildings.  This approach was successful in achieving a settlement of $1,675,000 at mediation in June 2010, over three times the amount the developer/builder team claimed would be sufficient to fully repair the buildings.

Hilltop Condominiums

In 2008, the Aldrich Eike firm obtained a $2.3 million dollar verdict for a 108-unit conversion condominium association for deck repairs against the conversion developer. Over 30 witnesses were called over the course of a complex six-week bench trial. The verdict reflected 100% recovery of deck damage. The Aldrich Eike Team also obtained a net attorney fee award of approximately $125,000 against the developer. After judgment was entered, the developer’s insurance company filed a related lawsuit claiming the Association’s award was not covered by insurance. 

In February of 2010, the Aldrich Eike Team took this second lawsuit to trial. The Association prevailed on the insurance coverage claim, received an additional attorney fee award of $414,350, and an award of post-judgment interest, resulting in a net award of over $2.8 million. This extraordinarily difficult case involved many complex insurance coverage issues, including issues never before decided by an Oregon court. The issues included developer coverage under a condominium policy, known loss exclusion, mold and fungus exclusions, allocation of covered and uncovered loss, and recovery of the underlying attorney fee award under the supplementary payments provision. The results of this case have already had significant impact on construction defect and coverage cases throughout Oregon.

Linden Village

Aldrich Eike represented the Association of Unit Owners at Linden Village Condominiums, a 30-unit, 15-building condo complex in Milwaukie. The ultimate result was settlement on the eve of trial for just under $1 million, which was sufficient to perform all necessary repairs. This settlement was obtained in spite of insurance coverage exclusion hurdles, complex defense motion practice, and a framing subcontractor who was unwilling to settle. After multiple mediations, Linden Village was successful in settling with the developer, who subsequently went to trial against the framing subcontractor. During that trial in January 2010, the developer hired attorney Kevin Eike as an expert witness to testify, which resulted in a verdict against the framer of more than double all previous settlement offers. The developer also used the Association’s expert and repair bids to present to the jury at trial.

Alderbrook

Aldrich Eike took over a construction defect case against a national builder that had been languishing for years. Within five months of takeover, the claim was successfully resolved for $1.5 million on the eve of arbitration. Aldrich Eike developed an accelerated and aggressive litigation/arbitration protocol, and repair analysis protocol, to successfully wrap up the project quickly and cost effectively. Full repairs, including complete tear-off and window replacement, were able to commence directly after settlement as the repairs were designed and funded, and the repair contractor bid had been accepted.

Marshall Wells

Aldrich Eike represented the association of owners at the Marshall Wells Lofts, a 7 story 1910 concrete warehouse which was converted into 167 luxury loft style homes located on 14th and Lovejoy in the prestigious Pearl District of northwest Portland on two separate occasions.  First, Aldrich Eike negotiated a resolution for a confidential settlement amount with the developer, general contractor, and design professionals who converted the building into loft style homes.  As part of that settlement process, the association and Aldrich Eike retained the services of a well known architectural building science professional to inspect the building with the purpose of determining the extent and cost of necessary repairs.  A few years later, when it was apparent the amount received was insufficient to repair the building, Aldrich Eike represented the association in pursuing a claim against the architectural building science professional who was hired to assist the HOA in the prior claim against the developer, general contractor and design professionals.  This claim against the architectural building science professional was resolved at mediation for a confidential amount after litigation had been filed and depositions occurred.

Orenco Station

Aldrich Eike represented multiple townhome associations (hundreds of units) and individual owners in a construction defect claim against the developer. Estimated repair costs were in excess of $15 million. Aldrich Eike put the developer on notice of the defects and then worked with the developer to negotiate a settlement in which the developer agreed to perform the full scope of repairs under supervision of the Association’s expert at no cost to the owners, without a release to the developer for the repair work, all without litigation. The developer then successfully performed over $15 million in repair work at no cost to the owners, and reimbursed the owners for the cost of their expert’s supervision of the repairs. This case is an example of the success of efficient lawyering and responsible developers.

Quimby Townhome Condominiums

Aldrich Eike represented the Quimby Townhome Condominium Association (30 units) in Northwest Portland with regard to defects and damages. A significant multimillion dollar settlement on the eve of trial was reached for the Association, allowing full (+) reimbursement of repair costs and attorney fees. This result was a premiere example of teamwork between the Association Board, Association Committees, Community Manager, and the Aldrich Eike firm to achieve a great result.

Springville Townhomes

After three weeks of jury trial, the Aldrich Eike firm achieved a multi-million dollar settlement for the Springville Townhomes Owners Association (71 units). Many homeowners testified in the litigation, in addition to experts and adverse witnesses from the developer/contractor side. This case is a proto-type for management of future Association trials in complex construction defect litigation. This was another example of great teamwork with the Association Board, Association Committees, Community Manager and Aldrich Eike.

Vista House Condominiums

Several years after turn-over, the owners of a premier condominium complex (24 units) in the west hills of Portland discovered potential problems regarding the weatherproofing of the structures. What the owners initially thought was a maintenance problem turned into a nightmare of construction defects. After nearly two years of contentious litigation, Aldrich Eike used its expertise to obtain a very substantial multi-million dollar settlement (one of the largest, if not the largest, condominium defect settlement in the Portland metro area) for the owners.

16th Place Condominiums

Aldrich Eike represented unit owners in the 16th Place Condominium Association (11 units) with regards to defects and damages. The case had serious insurance coverage questions involving bankrupt and shell corporations (including back up insurers), but was successfully settled. The owners obtained a mid-six figure settlement to reimburse repair costs.

Denney Road Row Homes

Aldrich Eike represented unit owners in the Denney Road Rowhomes Unit Owners Association (14 units) with regards to defects and damages. A seven figure settlement was achieved on the eve of trial and literally in the courthouse, allowing reimbursement of repair costs and attorney fees. Litigation was hard fought, and the unit owners were efficiently and effectively involved in obtaining the result.

Roth Estates

Aldrich Eike represented unit owners (5 owners) in Roth Estates with regard to construction defect and damages; and recently obtained a six figure settlement. The case was settled with minimal litigation.

Shiloh Heights Townhomes

Aldrich Eike represented unit owners in the Shiloh Heights Townhome Association (8 units in two buildings) in Southwest Washington with regard to defects and damages. The case had serious insurance coverage questions involving bankrupt and shell corporations, but was successfully settled. The owners obtained a mid-six figure settlement to reimburse repair costs.

Orenco East Village Condominiums

Aldrich Eike negotiated a settlement for the Orenco East Village Condominiums (210 units) in a litigation against the builder and developer of those condominiums. The large multi-million dollar settlement (one of the largest, condominium defect settlements next to Vista House, in the Portland metro area) is one of the most efficient obtained by Aldrich Eike. Fees were less than 10% of the total settlement. A significant factor in this great settlement was the work of the committees set up by the Association Board and Aldrich Eike, as well as the work of the community manager.

McKenzie Lofts Condominiums

Aldrich Eike negotiated a settlement for the Association (74 units) where the developer/builder/architect designed a repair plan, performed over $1,500,000 worth of repairs, and provided the owners with additional five year “bulletproof” warranty. Allocation of responsibility for one aspect of repairs (roof/deck structure) was arbitrated, with a successful result for the HOA.

Orenco Place Townhomes

Aldrich Eike recently settled a case for the association and owners of the Orenco Place Townhomes Association (64 units) with the developer and builder with respect to defects. After hard fought litigation, the case was settled for a favorable seven figure sum, allowing repairs and reimbursement of attorney fees. The pro active involvement of the Association Board, committees, and community manager was critical to the result.

Quail Hollow Townhomes

Aldrich Eike negotiated a settlement for the owners (6 units) where the builder/developer funded several hundred thousand dollars of repairs.

Bridgeton Road Townhomes

Aldrich Eike negotiated a settlement for the owners (6 units) where the builder/developer and other responsible subcontractors funded a repair contractor to perform several hundred thousand dollars of repairs to the townhomes.

Sellwood Commons Condominiums

Aldrich Eike prosecuted a construction defect and damage claim for unit owners and the association (10 units) regarding siding and deck problems at the Sellwood Commons Condominiums. The case was successfully settled. The owners obtained a mid-six figure settlement, enough to fund repairs and reimburse attorney fees.

View Point Rowhomes

In what started to be a siding, window and deck defect problem, the View Point Rowhome owners (3 units) discovered serious structural deficiencies with respect to retaining walls and the structure of their building, which forced them to move out. Aldrich Eike successfully negotiated a buy-back of the units from the developer, and a reimbursement of attorney fees and other costs, for a seven figure sum.

Pearl Lofts Condominiums

Owners in the Pearl District’s flagship condominium project (24 units) discovered extensive window problems and defects in the building envelope. The developer, general contractor, and window manufacturer attempted repairs, (which did not work), and then refused to undertake further repairs. The owners retained Aldrich Eike to prosecute the claim, which was one of the first construction defect cases filed for a condominium in the Pearl District. Combining an aggressive litigation and public relations strategy, a seven-figure settlement was obtained that allowed the owners to fully repair their units without financing, and reimburse the owners’ attorney fee expense.

Villas on the Lake I Condominiums

Aldrich Eike negotiated a settlement for the owners (14 units) where the builder/developer funded and performed several hundred thousand dollars of repairs to the condominiums.

La’Torre Condominiums

Dean Aldrich represented a general contractor in one of the first trials in the Portland metropolitan area regarding significant and widespread condominium construction defects. The general contractor had settled out with the homeowners (20+ units) for a seven figure amount and the builder then successfully went to trial in an action against the developer/architect and subcontractors in order to obtain contributions for those parties’ share of the damages. This case was initially responsible for establishing Dean Aldrich’s expertise in the field of construction defect litigation, which in turn led to the formation of the Aldrich Eike firm, P.C.

Back to top

Representative Defect Cases – Single-Family Homes

Catlin Crest Homeowners

Aldrich Eike represented owners of a home in the Portland West Hills with leaky windows. The homeowners filed a product defect and breach of warranty lawsuit against the window manufacturer and window supplier. During a 9-day jury trial in October 2010, the window folks attempted to blame the general contractor, framer, and siding subcontractor. The jury did not respond to these arguments. The jury found that the windows and the window installation instructions were defective, and that the window manufacturer did not honor its warranty, and that the fine print exclusions were not valid. The highest combined pretrial settlement offer from the window manufacturer and supplier was $10,000. The jury awarded the homeowners $573,956.43 in damages, and the judge awarded an additional $56,599.93 in prejudgment interest and costs, for a total award of $630,556.36.

Yamhill County Winery Owner

The owners of a winery in Newberg discovered construction defects immediately upon moving into their new home at the winery in September 2007. The owners immediately contacted the builder to discuss repairs, who in turn, demanded $80,000 more in addition to the full contract price which had already been paid. After two years of unsuccessful attempts to resolve the issues, the owners retained the Aldrich Eike firm to provide a defense for the payment claim and to pursue the construction defect claim in binding arbitration.

In July 2010, the Aldrich Eike Team defended the owners at arbitration against the contractor’s claim for nonpayment of the additional $80,000, while also asserting a counterclaim against the builder for failure to provide a proper accounting of the construction costs under the AIA contract. The owners prevailed on the accounting payment claim and the builder was only awarded $4,001 for costs that fell outside of the contract. The owners were also awarded $110,000 for attorney fees and costs for the accounting claim.

In September 2010, the Aldrich Eike Team arbitrated the construction defect claim. The owners were ultimately awarded $125,000, including $20,000 in compensation for the cost of investigation of the defects.

Street of Dreams Homeowner

Aldrich Eike represented an owner of a $2.4 million Street of Dreams home in the southeast Portland hills in defense of a $676,000 nonpayment claim filed against the owner by the builder.  In addition to the lawsuit filed against the homeowner by the builder, the home had multiple liens filed against it by subcontractors and suppliers which were also defended by the Aldrich Eike firm. A countersuit by the homeowner was filed against the builder for construction defects.  The case was brought to verdict after a 5-day arbitration.  After hearing both the builder’s payment claim and the homeowner’s defect counterclaim, the result was a verdict of $4,575.66 net to the homeowner, plus a reimbursement of $99,500 in attorney fees.

Southern Oregon Homeowner

Aldrich Eike represented two separate homeowners in an over age 55 planned community located just east of Grants Pass. During the real estate boom of the mid 2000s, a California developer bought this 28-lot subdivision and promised buyers 24-hour security, a clubhouse, and a new nearby medical facility. After building out half of the 28 lots, the developer lost funding and abandoned the project, leaving owners well short of what they were promised. To add insult to injury, the homes were improperly constructed and could not be sold. In both cases, the Aldrich Eike firm was able to work with clients, adverse counsel from southern Oregon, and a Josephine County retired judge mediator to negotiate favorable resolutions, providing clients with much needed resources to fix their homes.

West Linn Acreage

Homeowners hired a general contractor to construct their dream home in 1999 on a 60-acre estate in West Linn, Oregon. Within a year after construction, they were experiencing significant water intrusion issues.  Unbeknownst to the homeowners until discovered in litigation by the Aldrich Eike firm attorneys, the builder had experienced water intrusion that had damaged interior finishes before the home was even complete and had covered up the damage. The builder and his subcontractors came back and attempted repairs on repeated occasions after the homeowners moved in, but the repairs were unsuccessful. The homeowners hired the Aldrich Eike firm to represent them in pursuing construction defect claims against the builder of the home. Repairs were significant and included complete removal and replacement of siding, and removal and reinstallation of all windows and doors on the French estate style home. Repairs were completed before the case was settled/resolved in order to eliminate the risk of spending more on repairs than ultimately recovered on the case.   The Aldrich Law office obtained a settlement of over $300,000 at mediation, which provided the necessary funds to reimburse the homeowners for money spent on repairs.

West Linn Homeowners

West Linn homeowners hired a general contractor to construct their dream home. Within a year after construction, they were experiencing significant water intrusion issues. The builder came back and attempted repairs, but the repairs were unsuccessful. The homeowners hired the Aldrich Eike firm to represent them in pursuing construction defect claims against the builder of their custom home. The Aldrich Eike Team worked with the defense in selecting a repair contractor and battling over the repair scope. Repairs were significant and included complete removal and replacement of siding, removal and reinstallation of all windows and doors, and reconstruction of five decks on this four-story home. Aldrich obtained a settlement of $549,500, more than full recovery of repair costs, at a judicial settlement conference just prior to trial in March of 2010.

Forest Heights Homeowner

Aldrich Eike represented a Forest Heights homeowner in a complex construction defect claim against the original builder and its subcontractors, the window manufacturer, the realtor, the home inspector, and repair contractors. This homeowner purchased her home from a former Portland Trailblazer, and as part of the sale, commissioned a home inspection, during which problems with the EIFS siding and decks were discovered on the rear elevation. The seller gave a credit of approximately $150,000 for repairs found by the home inspector. The repair contractors performed the siding and deck repairs, but failed to remove and reintegrate the windows with the siding. Further complicating matters, the realtor for the client was from the same office as a realtor who handled a prior sale of the same home. This realtor had information that inspections had been done during the prior sale only two years earlier, which called for complete removal and replacement of the EIFS siding on all four elevations of the home, but failed to disclose this information to the client. Another obstacle to resolution (and the subject of summary judgment motions) was an agreement signed by the client to release any claims against the seller, and also to assign to the seller any claims against the original contractors. The Aldrich Eike Team was successful in contacting the former seller and obtaining a declaration stating that he never meant the agreement to be a present release or assignment, and reassigning the claims back to the client.

After engaging in hard-fought litigation, including extensive document discovery, depositions of all parties, two rounds of summary judgment motions by all defendants, and one mediation, the Aldrich Eike firm was successful in obtaining $222,000 in settlement at mediation just two months prior to trial.

Salem Homeowners

Aldrich Eike represented Salem homeowners in a construction defect claim against the general contractor, who was the homeowners’ own company. This home was originally built as part of a 1997 Salem Tour of Homes, and then put on the open market to be sold. After over 15 months on the market, the owner of the general contractor company decided to purchase the home for his and his wife’s personal use. The homeowners began to experience leaks after moving into the home, and sued their own company for the defects. Aldrich Eike was able to obtain $85,000 in settlement from the client’s company’s insurer and subcontractors at a judicial settlement conference.

Skyline Heights Homeowner

Aldrich Eike represented the owner of a large luxury home in claims against the builder of the home. The homeowner, a local Real Estate Broker, had contracted with the builder for construction of the custom home and was involved intimately in the construction process, yet was unaware of the widespread defective construction until the home started leaking and consultants were hired to evaluate the construction of the home. The home had significant deck and structural issues, as well as exterior envelope failures, which included cultured stone and lap siding. The case resulted in a $263,000 settlement, enough to fully repair the home and reimburse the homeowner for attorney fees.

West Hills Homeowner

Aldrich Eike represented a West Hills homeowner in a construction defect issue that involved significant structural issues with a constructed elevated concrete driveway. In an effort to avoid litigation, the Aldrich Eike firm convinced the contractor’s insurance company to enter into a statute of limitations tolling agreement while damages and liability were evaluated. After proving to the insurance company that the driveway was improperly constructed and providing repair bids establishing damages, the case was ultimately settled without the need of filing a stressful, time consuming, and expensive lawsuit. After settlement monies were received, the home was fully repaired.

Forrest Heights Homeowner

Aldrich Eike represented a Forrest Heights homeowner in a construction defect action involving their custom home. The case involved repair costs in excess of $220,000 which involved completely removing all of the Exterior Insulation Finish System (EIFS) synthetic stucco siding from all four elevations of the home, removal and reinstallation of over 50 windows, reconstructing three decks, and performing significant excavation to remedy drainage defects. After filing suit, documentary discovery, depositions, and two mediations, the case was favorably resolved with a $252,000 monetary settlement to our Client on the eve of trial.

Skyline Heights Homeowner

Aldrich Eike represented a Skyline Heights homeowner in their construction defect action involving their custom home against their builder and its subcontractors. Repairs were extensive (in excess of $300,000) and involved removing and replacing all of the defectively installed brick veneer and cedar siding, removal and reinstallation of the windows, and reconstructing both traditional and waterproof membrane decks. The case was favorably resolved with a $325,000 monetary settlement at mediation.

West Hills Homeowner

Aldrich Eike represented a West Hills homeowner in a construction defect action involving their custom home that was built in 1997. Facing repair costs in excess of $100,000, a claim was submitted against the builder and the builder’s insurance companies. After filing suit, documentary discovery, and depositions, the case resolved at mediation with a monetary settlement in excess of $150,000.

Back to top